Page 28 - Pelan Strategik ICT
P. 28
2012 - 2014 THE CENTRE FOR INFORMATION TECHNOLOGY - ICT STRATEGIC
PLAN
YEAR 2012 – 2014 KPI
Results Action Plan Time
Remarks
Period
1.6 Upgrading SAN Storage to add storage Storage capacity of the
High-performance capacity 5TB/year existing SAN hardware is
data centre Jan 2012 – now approaching
Dec 2014 maximum capacity
Upgrade database server SIS 9i RAC, 9i and
Apr 2012 –
FIS HRIS 9i to 10g/11g database
Mar 2013
Upgrading Oracle Application
Apr 2012 –
Server (OAS)
Mar 2013
Jun 2013 –
Acquire a new Load Balancer Dec 2013
To build a Centralised Monitoring Centre Jun 2014 –
Dec 2014
Acquire data replication software / Jan 2013 –
hardware along with installation services Dec 2013
1.7 To Develop new data centre infrastructure
New Data Centre (Renovation costs, UPS, Network, Genset, Jan 2014 –
Fire Prevention System, the Command Dec 2014
Centre, precision AC, etc.)
1.8 • Upgrade Infrastructure
Jun 2012 –
Security and Data Backup
Dec2012
Availability • Replicating Moodle DB (pilot)
1.9 Upgrade and replace the old server (RMIS,
Upgrading older UMMIS, UMmail DB, Moodle E-Learning, Jan 2013 –
hardware Student Portal) Dec 2013
1.10 Upgrade infrastructure
Webhosting Webhosting Jun 2012 –
Service Dec 2012
Improvement
26
26